SWR
– Current
– Finished
– Future
Kolar ? Chikkaballapur gauge conversion
Description: Proposed manual laying and linking of BG Track & Ballast works Location:
Hubli – Ankola Major Work
Description: Construction of major Bridge No. 42 as 5 x 18.30m clear span with PSC girders on well foundation. Location: Khalgatgi, Karanataka
Kolar – Chikkaballapur Gauge Conversion
Description: Proposed manual laying and linking of BG Track & Ballast works Location: Kolar, Karnataka Date of Allotment:13/07/2011 Date of Completion : 31/12/2013
Gadag – Solapur Track Work
Description: Gauge Conversion from MG to BG –Execution of Earthwork, side drains, catch water drains and other Miscellaneous building works. Location: Gadag, Karnataka Date of Allotment: 18.05.2007 Date of Completion:...
Hubli – Bellary section
Description: Jacketing of pires and abutments for strengthening of Bridges Location: Bellary, Karnataka Date of Allotment: 08.10.2007 Date of Completion: April 2010
Hubli – Kundagol Section
Description: Construction and commissioning of crossing station between Hubli and Kundagol, including earthwork, track work and other misc. works Location: Kundagol, Karnataka Date of Allotment: 02.04.2008 Date of Completion: 19.01.2010
Hubli – Hebsur Doubling
Description: Proposed Construction of New subway in cast box pushing Rail and Roll method Location: Hebsur, Karnataka Date of Allotment: 01.05.2008 Date of Completion: 30.05.2010
Dharwad – Kambarganvi – 3
Description: Construction of major Br. No. 176 PSC girders with open foundation including approach earth work and Misc. Works Location: Kambarganvi, Karnataka Date of Allotment: 22.10.2008 Date of Completion: 15.05.2011
Dharwad – Kambarganvi – 2
Description: Construction of ROBs No 179 & 187, RCC portal of square returns with open foundations, pile foundation and earthwork Location: Kambarganvi, Karnataka Date of Allotment: 25th November 2008 Date...
Hassan – Bangalore New BG Line
Description: Hassan – Bangalore new BG line: Construction of major bridges, ROBs, RUBs other connected works in Yediyuru and Hirisave section. Location: Adichunchungiri, Karnataka Date of Allotment: 3rd September 2011
Ginigera – Raichur New BG Line
Description: Earthwork and Construction of Bridge and electrical LT power lines Location: Ginigera, Karnataka Date of Allotment:11th mat 2012
Hubli Division – Subway
Description: Extension of subway in hubli railway station for a length of 19Mtrs Location: Hubli, Karnataka Date of Allotment: 29th Jan 2013
Hubli yard – Track Work
Description: track linking, laying, transportation of rails, sleepers, dumping of ballast and other Misc. works Location: Hubli, Karnataka Date of Allotment: 18th May 2012
Dharward – Kambarganvi – 1
Description: Construction of Patch Doubling, Earthwork in embankment/ cutting, construction of minor bridges Location: Kambarganvi, Karnataka Date of Allotment: 18th September 2007 Date of Completion: 28th February 2012
Hosadurga – Chikjajur Section
Description: Patch doubling work- construction of minor bridges, Limited height subways, Road approaches, earthwork, side drains etc. Location: Chikjajur, Karnataka